Table
ProjCDSTaskImport
Project integration table for tasks
Holds project task data brought in from Dataverse. Each record has a task ID, parent task ID, work breakdown structure details and the project. It can also link to an activity.
- Table name
ProjCDSTaskImport- Module
Project management and accounting- Table group
Transaction- Table type
Regular- Data per company
Yes- Configuration key
Project- Primary index
None- Replacement key
None- Key fields
None- Model
Foundation
Fields (14)
| Field and description | Type / EDT / enum | Mandatory | References | In public entities |
|---|---|---|---|---|
ActivityNumberActivity linked to the task. | String (50)smmActivityNumber | No | smmActivities.ActivityNumber | None |
DataAreaIdThe company (legal entity) that the record belongs to. System field. | String (4)DataAreaId | No | None | |
ElementNumberElement number of the task. | StringElementNumber | No | None | |
HierarchyIdID of the hierarchy that the task is in. | StringHierarchyIdBase | No | None | |
NameName of the task. | String (60)Name | No | None | |
ParentElementNumberElement number of the parent task. | StringElementNumber | No | None | |
ParentTaskIdID of the task above this one in the hierarchy. | Guid | No | None | |
PartitionA system field for the data partition. In most environments every record has the same value. System field. | Int64Partition | No | None | |
ProjectIdProject that the task belongs to. | String (20)ProjId | Yes | ProjTable.ProjId | None |
RecIdA unique number that the system gives to every record. Other tables often use it to point to this record. System field. | Int64RecId | No | None | |
RecVersionA system number that changes each time the record is updated. It is used to detect conflicting updates. System field. | IntegerRecVersion | No | None | |
TableIdA system number that identifies the table. System field. | IntegerTableId | No | None | |
TaskIdUnique ID of the task. | Guid | Yes | None | |
WbsIdWork breakdown structure ID of the task. | String (100) | Yes | None |
Indexes (1)
TaskUnique, alternate key.
Relations (3)
Each relation joins ProjCDSTaskImport to another table on the fields shown.
ProjTable→ProjTableJoin on
ProjectId = ProjTable.ProjIdMany ProjCDSTaskImport records → exactly one ProjTable record
smmActivities→smmActivitiesJoin on
ActivityNumber = smmActivities.ActivityNumberZero or one ProjCDSTaskImport record → zero or one smmActivities record
parentSmmActivities→smmActivitiesJoin on
ActivityNumber = smmActivities.ActivityNumberZero or one ProjCDSTaskImport record → zero or one smmActivities record
Get this data out
No public entity reads from ProjCDSTaskImport. Its data is only reachable through the application, a custom entity or a database export.
Need help with ProjCDSTaskImport in a report, an integration or a migration? Talk to Dr Dynamics.